East Side Light Rail Time & Budget

1978  Forecast 1990 Actual Difference
Ridership 42,500 19,700 54% under ridership projection
cost of MAX $172 million $266 million 55% over construction budget
operating costs for MAX $3.8 million $5.8 million 53% over  operating budget
opening date 1983 1986 3 years late

Table created from data in STUDY SAYS MAX CALCULATIONS WERE WRONG , The Oregonian December 29, 1989

From Trimet's FactSheet

Eastside MAX—Blue Line

The 15-mile Eastside MAX line opened in 1986, stretching east from downtown Portland to Gresham. The project was completed on time and under budget.